A unique approach to a reformer expansion.

  • Shop fabricate new roof, wall, and floor panels, structural steel, etc. including shop installed insulation
  • Construct furnace expansion, including walls, tubes, etc., during operation
  • Remove existing wall during short turn-around
  • Increase tubes from 240 to 280
  • Increase burners from 108 to 126
  • Increase in reformer capacity of 16.6%
  • Overall production increase from 1950 tons per day to 2130 tons per day
 