Project Scope

The scope of this project was to revamp and redesign the existing Crude Heater to accomplish the following:

  • Eliminate the existing Heat Recovery Boiler
  • Reuse as much existing equipment as possible
  • Add new Air Preheat System to Furnace
  • Replace existing burners with Low NOx Burners
  • Increase Furnace Capacity to meet future 30,000 BPD case
  • Maximize overall unit fuel efficiency
  • Replace all tubes which had been deemed to be below required wall thickness